Parking and Access Requirements

The mobile CT trailer unit weighs up to 23 tonnes. The trailers are approximately 14 metres long and 2.6 metres wide (up to 4.25 metres wide with the sides fully extended).

Access consideration must be given to the tractor, the patient lift, the stairs and the belly compartments, for patient entry and trailer service. A total paved area of at least 6 x 20 meters is recommended for tractor access and patient handling.

It is important, especially with mobile CTs, that the site is level. It is possible to accommodate a fall of no more than 150 mm over the length and 50 mm over the width of the unit. Road quality surface for the site is acceptable provided that there are no drains, ducts or other below ground structures that could be damaged by the weight of the scanner.

When parked, the unit uses two front hydraulic jacks and two fixed height stands in the rear, for stabilising purposes or four fixed height stands if a full size pad is available. The trailer is placed on ‘spreader plates’ that spread the load to avoid damage to the road surface.

In cases where the ground cannot support the scanner in the proposed location, a concrete support pad constructed to ensure a level surface capable of accommodating the weight of a mobile scanning unit is recommended.

 

Pad Requirements

The following is a list of recommendations and requirements for a concrete support pad however, due to varying site conditions a local contractor should be consulted for actual pad design.

Support Pad
A full pad measuring 3.04m x 13.68m is required. The support pad must be level (no more than 150 mm variations over length and 50 mm variation across length) to insure proper operation of the Mobile CT unit.

Service Pad
A full pad measuring 6.40m x 15.50m is recommended to provide service access. This is optional if space is available.

Steel Reinforced Concrete Pad
Maximum 20kg/m2 of steel.

 

Power Requirements

Mains Electrical Supply
A single electrical power source is required for operation of the CT system.
3/N/PE AC 400V service fused at a minimum of 125A per phase, although a supply of 175A per phase is preferable.

Configuration
Three phase, five wire, wye connection, with neutral and ground.
(5 wire 3/N/PE AC 400V)

Load Regulation at Line Frequency
Wires are to be sized such that the line voltage drops from the power source to the mobile unit is less then 2% of the nominal voltage for the rated load of the mobile unit.

Frequency
50 Hz + 0.5 Hz.

Phase balance: 2% maximum of lowest phase-to-phase voltage.
Maximum Voltage Variation: + 5% from a nominal steady state (under the worst case conditions of line voltage).

Connector type
The mobile unit is supplied with a 35'-0" (10.668m) useable power cable and male conductor. AMIS scanners come equipped with both Marechal DS2 and Lewden PM125/808 type male connectors. The Lewden connector is a version of the CeeForm CEE 17 125A 400V (red) connector.

Customer Facility
The customer facility must have the matching receptacle. Unless otherwise specified, the receptacle type to be used must be either a Marechal DS2 or the CEE17 125A female connectors.

 

Mobile Grounding Requirements

Ground Wire
An insulated ground conductor sized in accordance must be installed between the facility vault and the mobile system ground bus location in the power distribution unit.

Special Ground Note
The mobile unit includes an earth driven ground rod within 5’-0” (1.524m) of the facility power receptacle. A grounding cable of a minimum #1/0 AWG must be connected between the grounding rod and the grounding pin of the facility power receptacle, and another cable to be kept as short as possible, and must not exceed 8’-0” (2.4384m) in length. A separate grounding conductor must still be run with the phase conductors to the source of the power from the grounding pin of the hospital power receptacle.

 

Additional Requirements

Radiation Shielding
Factors such as proximity to buildings, and occupancy of the surrounding areas must be considered. The mobile unit has been designed to provide radiation shielding for the areas adjacent to the procedure room. A proprietary and highly effective lead shielding system is installed in the gantry and patient prep room walls. Lead shielded windows are installed in the patient prep and gantry room walls and doors.

Water requirements
The mobile unit does not utilize a water tank. All water that is needed is obtained through a facility connection. The facility connection provides the needed water for both the humidifier and an onboard sink. The mobile unit will be supplied with a ¾” (1.905 cm) diameter, 20’-0” (6.096m) long hose terminated with a ¾” (1.905 cm) I.P.S male threaded hose connector located on the drivers side of the mobile unit. The facility must provide a ¾” (1.905 cm) female connector and a water supply.

Telephone service
Two telephone lines are required for the operation of the mobile unit: a normal telephone line to enable the scanner to communicate with the hospital, and (optional) a dedicated direct line of modem connection. In the trailer belly compartment, there is a Hubbell phone connection socket. An adaptor must be provided to connect from the local phone socket to the Hubbell.

 

Site Checklist

This checklist is provided to help you prepare your site for the mobile unit. If for any reason you cannot meet these points contact AMIS for possible alternatives.

  • Trailer access route determined.
  • Trailer exit route determined.
  • Tractor access checked.
  • Service access clear around trailer.
  • Support pad.
  • Communication lines.
  • Electrical service checked and meets specs.
  • Grounding checked.
  • Mains impedance checked.

 

Mobile CT Drawings

Download a complete Mobile CT Unit site planning guide. - 4 minute download.

 

Back to Top

 Back to Site Planning Guide

 

 

 

|Home|  |Mobile Units|  |Site Planning Guide|  |Visual Gallery|  |Special Offers| |About Us|

|Calendar of Events|  |Contact Us|  |Site Map|  |Site Designed By|